Sunday, July 5, 2009

Industrial Training Week 11

Summary of week 11

Monday – 29 June 2009

Preparation and submission of tender document for project Rancangana Tebatan Banjir Sungai Linggi, Negeri Sembilan - Package 3

Preparation and submission of Engineer's Estimate for project Rancangana Tebatan Banjir Sungai Linggi, Negeri Sembilan - Package 3

Tuesday - 30 June2009

Assisting Nasrullah in preparing Term of Reference for LCCT project


Wednesday - 1 July 2009

Drawing the river section for Sungai Rasa using AutoCad


Thursday - 2 July 2009

Preparing Tender Evaluation and Defect Checklist for new office renovation

Attended Talk on Training on Dam Operation, Maintenance and Safety Monitoring organised by MARDITech and coordinated by RPM Engineers

Talk tittled Dam Instrumentation

Friday - 3 July 2009

Preparation of Tender Evaluation for new office

Helping out the report preparation for Kano Project

Sunday, June 28, 2009

Industrial Training Week 10

Summary of week 10

Monday – 22 June 2009

Submittion of video storyboard of Raising of Timah Tasoh Dam, Perlis to Managing Director, Ir. Mohd Adnan for review and discussion

Reviewing the video storyboard

Preparation of report


Tuesday - 23 June2009

Discussion of video storyboard of Raising of Timah Tasoh Dam, Perlis with Managing Director, Ir, Mohd Adnan. Comments

a) Need to be more technical

b) Include specification

c) Step by Step explanation

Review of video story board

Wednesday - 24 June2009

Editing the video storyboard of Raising of Timah Tasoh Dam, Perlis

Include photos taken on site and using Google Sketch Up

Preparation of Tender Document for Rancanagan Tebatan Banjir Sungai Linggi, Negeri Sembilan - Package 3

Thursday - 25 June2009

Attended brieffing to contrtactor by Wong Phey Yean for project Rancangan Tebatan Banjir Sungai Kangsar/ Sungai Lawin, Perak. Menaik Taraf Sungai Kangsar, Phase 1 Peringkat 2 at JPS Perak, Kuala Kangsar

Included site visit and site survey

Preparation of Tender Document for Rancanagan Tebatan Banjir Sungai Linggi, Negeri Sembilan - Package 3


Friday - 26 June 2009

Preparation of Tender Document for Rancanagan Tebatan Banjir Sungai Linggi, Negeri Sembilan - Package 3

Helping out Azizi, draftsman to complete the drawing for tender submittion

Sunday, June 21, 2009

Industrial Training Week 9

Summary of week 9

Monday – 15 June 2009

Calculation of excavation for Sungai Linggi to include in BQ.

Attended Staad Pro presentation version V8i and PROKON

Plotting and calculating the area for land aquisition for project Rancangan Tebatan Banjir Sungai Linggi


Tuesday - 16 June2009

Plotting and calculating the area for land aquisition for project Rancangan Tebatan Banjir Sungai Linggi

Analysis using HEC-RAS to obtain Q versus WS elevation for Magaga, Tomas and Watari Dam


Wednesday - 17 June2009

Attended talk held by Jurukur Perunding. Introducing 3 new products

a) Geoeye

b) Nextmap

c) Navcom

for GIS purposes

In house training by Ashrin titled "How to Write a Good Letter."


Thursday - 18 June2009

Analysis Using HEC-RAS with new information of Magaga, Watari and Tomas Dam

Learning of Sketch Up

Friday - 19 June 2009

Learning of Sketch Up

Half day~

Sunday, June 14, 2009

Industrial Training Week 8

Summary of week 8

Monday – 8 June 2009

Geotechnical analysis for piling works for outlet structure at pond near Pengkalan Durian, project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan. Package 3

Preparation of Tender Document for project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan - Package 3


Tuesday - 9 June 2009

Reviewing outlet stucture design with Nasrullah

Reviewing data from HEC-RAS for the outlet stucture design with Nasrullah

Wednesday - 10 June 2009

Design of Outlet Structure with Nasrullah

Calculating the volume of works for

a) Excavation

b) Trimming and Turfing

c) Road

d) Bund

e) Drainage

for Parit Haji Yusof and Pematang Pasir to complete the Bill of Quantities in Tender Document for project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan, Package 3

Discussed story board for video preparation of Raising of Timah Tasoh Dam, Perlis with Ir Mohd Adnan

Obtained detail information of how the saddle dam was raised from En Rizwan

Thursday - 11 June 2009

Revising the video preparation of Raising of Timah Tasoh Dam, Perlis

Friday - 12 June 2009

Revising the video preparation of Raising of Timah Tasoh Dam, Perlis

Calculating the number of piles required for the outlet structure based on the ultimate load, Qu obtained from the previous calculation

Sunday, June 7, 2009

Industrial Training Week 7

Summary of week 7

Monday – 1 June 2009

Reinforced concrete design for wall for drainage at Parit Haji Yusoff for the project, Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan using,

1) Hand calculation

2) PROKON


Review of the video making of Raising of Timah Tasoh DAm, story board

Tuesday - 2 June 2009

Using Sigma-W to analysis the soil stability for sheet pile


Meeting with JPS Negeri Selangor to submit and dicuss on the issue of wallguard wall at Sungai Rasa, Klang

Wednesday - 3 June 2009

Continuation of analysis and esign using PROKON and SIGMA - W

Thursday - 4 June 2009

Geotechnical analysis for piling works for outlet structure at pond near Parit Haji Yusof, project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan

Folding 160 A1 drawing for submittion for the project Raising of Timah Tasoh Dam, Perlis


Friday - 5 June 2009

Continuation of folding A1 drawings for submittion for the project Raising of Timah Tasoh Dam, Perlis


Preparation of Tender Document for project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan - Package 3

Attending the in-house training by Wan Yusnira on Hydrological Procedure 1

Saturday, May 30, 2009

Industrial Training Week 6

Summary of week 6

Monday – 25 May 2009

Pond and bund design for the project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan – Package 3. Using Rational Method Q = CiA

Using HEC-RAS to design the drain size for river diversion from Parit Haji Yusof to Sungai Linggi using 2 different section

1) Earth Drain

2) Concrete Drain

Tuesday - 26 May 2009

Using HEC-RAS to determine the bund height at Sg Solok with data obtained from HEC - HMS

Discussion with Ir. Liam regarding channelization works for the project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan – Package 3

1) Proposed berm cutting

2) Environmental friendliness

Reinforce concrete design and geological analysis for wall and bund works around river diversion

Wednesday - 27 May 2009

Continuation on RC design and geological analysis for wall and bund design

Meeting JPS Selangor and JKR regarding the project Mengatasi Banjir di Taman Rashna dan kawasan perindustrian berhampiran daerah Klang.

Issue discussed was on

1) The works of river channelization from the bridge extend has clashed with JPS scope of work

2) Due to works done by JKR, the existing wellguard wall has slanted

3) Discussion on who is responsible

Thursday - 28 May 2009

Site visit to Sg Rasa Klang for the project Mengatasi Banjir di Taman Rashna dan kawasan perindustrian berhampiran daerah Klang.

Issue discussed was on

1) Removal of slanted wellguard wall

2) The end cap design for the wellguard wall

3) The maximum allowable bend for design

Friday - 29 May 2009

Meeting JPS Negeri Sembilan regarding the issue of extra excavation volume for project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan – Package 1

Preparation for submission of 10 copies of Final Report and Alternative Ddesign Wellguard Wall without Tie Back to JPS Selangor for project Kerja-kerja Tebatan Banjir Sg Rasa di Taman Rashna dan kawasan perindustrian berhampiran daerah Klang, Selangor

Sunday, May 24, 2009

Site Visit 20 May 2009


Some pictures taken during the Site Visit on 20 May 2009

Brieffing by contractor Ir Fauzi regarding the project and progress to JPS Malaysia

Survey on the abbandon quarry

One of the three dreggers located along the river

Survey on the stockpiling of sand near the river bank