Saturday, May 30, 2009

Industrial Training Week 6

Summary of week 6

Monday – 25 May 2009

Pond and bund design for the project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan – Package 3. Using Rational Method Q = CiA

Using HEC-RAS to design the drain size for river diversion from Parit Haji Yusof to Sungai Linggi using 2 different section

1) Earth Drain

2) Concrete Drain

Tuesday - 26 May 2009

Using HEC-RAS to determine the bund height at Sg Solok with data obtained from HEC - HMS

Discussion with Ir. Liam regarding channelization works for the project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan – Package 3

1) Proposed berm cutting

2) Environmental friendliness

Reinforce concrete design and geological analysis for wall and bund works around river diversion

Wednesday - 27 May 2009

Continuation on RC design and geological analysis for wall and bund design

Meeting JPS Selangor and JKR regarding the project Mengatasi Banjir di Taman Rashna dan kawasan perindustrian berhampiran daerah Klang.

Issue discussed was on

1) The works of river channelization from the bridge extend has clashed with JPS scope of work

2) Due to works done by JKR, the existing wellguard wall has slanted

3) Discussion on who is responsible

Thursday - 28 May 2009

Site visit to Sg Rasa Klang for the project Mengatasi Banjir di Taman Rashna dan kawasan perindustrian berhampiran daerah Klang.

Issue discussed was on

1) Removal of slanted wellguard wall

2) The end cap design for the wellguard wall

3) The maximum allowable bend for design

Friday - 29 May 2009

Meeting JPS Negeri Sembilan regarding the issue of extra excavation volume for project Rancangan Tebatan Banjir Sungai Linggi, Negeri Sembilan – Package 1

Preparation for submission of 10 copies of Final Report and Alternative Ddesign Wellguard Wall without Tie Back to JPS Selangor for project Kerja-kerja Tebatan Banjir Sg Rasa di Taman Rashna dan kawasan perindustrian berhampiran daerah Klang, Selangor