Monday - 4 May 2009
Using HEC_RAS for modeling and analysis for further understanding on how the program runs
Tuesday - 5 May 2009
Drawing the soil profile using AutoCAD for the project Rancangan Tebatan Banjir Sg. Linggi - Pakej 3 for further analysis with Geo-Slope
1) From Chainage 1 to Chainange 55
2) 29 boreholes were located along the section
3) Determination of the SPT value
Wenesday - 6 May 2009
Calculation of the amount of volume for the works
1) Culvert
2) Drainage
3) Road
for the project Rancanagan Tebatan Banjir Sg. Linggi - Pakej 2
Checking of the detailed design report for finalization and submittion for the project Rancanagan Tebatan Banjir Sg. Linggi - Pakej 2
Thursday - 7 May 2009
Went to the new office of RPM located in Kota Damansara for
1) Measurement of the office
2) Ideas of office design
3) Photo taking of design by others
Friday - 8 May 2009
Video preparation for the project Raising of Timah Tasoh dam, Perlis. Listing of items to be included in the video such as
1) Background or History of the site
2) Problem
3) Solutions
4) Detailed Design
5) Advantages
Preparation for submittion of detailed design report fot the project Rancanagan Tebatan Banjir Sg. Linggi - Pakej 2
Planning of new office layout using AutoCAD
Saturday - 9 May 2009
Attended bowling activity held by RPM sports club in Tropicana gold club house